Guides · Construction · 7 min read

Construction draw schedules: how builders actually get paid

How construction loan draws are structured, inspected, and funded — the standard stage breakdown, lien waivers, retainage, and how to keep a build from stalling between draws.

The principle: money follows the work

On a construction loan, land and closing costs fund at closing, and the construction budget is held by the lender and released in stages as work is completed and verified. Nobody hands a builder the full budget on day one — not because builders aren't trusted, but because the collateral only becomes worth the loan as the building goes up.

A standard stage breakdown

Draw schedules are negotiated from your budget, but most ground-up schedules follow the same construction logic:

StageTypically coversRough share of budget
1. Site & foundationExcavation, footings, foundation, backfill15–20%
2. Framing & roofFraming, sheathing, roof dried in, windows20–25%
3. Mechanical rough-inPlumbing, electrical, HVAC rough, inspections passed15–20%
4. Insulation & drywallInsulation, board, tape, prime10–15%
5. Interior finishesCabinets, trim, flooring, fixtures, paint20–25%
6. Final & punchFinal inspections, certificate of occupancy, punch list5–10%

Two rules make a schedule workable: every stage must be verifiable by inspection ("foundation poured and passed" can be checked; "30% complete" cannot), and no single stage should be so large that a disagreement freezes the whole job.

What a draw request needs

Retainage, and why it exists

Most construction lending holds back a slice of each draw — commonly five to ten percent — until substantial completion. It is not distrust; it is the mechanism that keeps the last five percent of a job, which is the hardest five percent, from being abandoned. Build retainage into your own subcontractor agreements the same way, or you will finance it out of your own pocket.

The change-order problem

Change orders are where budgets and draw schedules quietly diverge. The owner wants a different tile, the framing reveals rot, the town requires a detail nobody priced. Each change moves money between budget lines that the draw schedule is built on.

Communicate change orders to your lender when they happen, not at the next draw request. A documented change is an adjustment; an undocumented one is a discrepancy.

Keeping the schedule moving

For the budget that sits underneath the schedule, see where construction budgets actually leak, and run your numbers on the construction cost calculator.

Have a project ready to finance?

Send the address, the budget, and the timeline — you will get a straight answer, not a maybe.

Submit a Project

Common questions

How many draws does a typical construction loan have?

Most ground-up construction loans use five to eight draws tied to completion stages — foundation, framing, mechanical rough-in, drywall, and finishes are the common markers. Too few draws concentrates risk; too many creates administrative drag for everyone.

What is retainage on a construction loan?

Retainage is a percentage — often five to ten percent — held back from each draw until the project is substantially complete. It protects against a contractor walking off before punch-list items are finished, and it is released at final inspection.

Do I pay interest on the full construction loan before it is drawn?

It depends on the lender. Some charge interest on the full committed amount from closing; others charge only on funds actually disbursed. This materially changes your carrying cost — ask the question directly and get the answer in writing.

How long does a construction draw take to fund?

A well-run process runs days, not weeks: request, inspection within a few business days, then funding. Ask any lender their actual average before you close — a slow draw desk turns into idle crews and blown schedules.

Keep reading

Fix & Flip

How ARV is determined on a fix-and-flip, why the appraiser's number usually lands below yours, what a low ARV …

Cost Control

The line items that actually blow construction budgets, practical cost-control moves that don't cheapen the bu…

Rentals

How to underwrite a rental like a lender — net operating income, DSCR, cash-on-cash and cap rate, plus the ope…